UPDATES are under each project below.
In 2025 the Village has contracted for maintenance of two public pedestrian paths located on the east side of Glen Brooke Drive and Jackson Drive.
- Glen Brooke Drive Path
- Segment - East side of Glen Brooke Drive, from Glen Hill Drive (offset 125 feet south) to Sherman Road.
- Scope - To remove the existing pavement, stabilize soils, regrade, and place new pavement.
- Contractor - Poblocki Paving.
- Timeline - Pavement removal will occur the week of 7/14. Stabilization and regrading of soils will occur the weeks of 7/28 and 8/4. Paving is scheduled to occur the week of 8/11.
- UPDATE on 8/21 - Paving will occur the week of 8/25
- UPDATE on 9/15 - All paving and lawn restoration is complete as of 9/11
- Jackson Drive Path
- Segment - East side of Jackson Drive, from the terminus of Hickory Lane Park Path south to Sherman Road.
- Scope - Crack filling and seal coating.
- Contractor - Johnson and Sons.
- Timeline - TBD, completion on or before 10/31.
- UPDATE on 8/21 - Patching will commence the week of 8/25. Seal coating will commence the week of 9/1.
- UPDATE on 9/15 - All path maintenance work is complete as of 9/12.
Pedestrians are asked to avoid the project work zones until after the projects have concluded. Please contact DPW Staff at 262-677-0707 if you have any further questions or concerns.